Lake Front D
Lake Front D is a residential project by Janapriya Projects in Kapra, Keesara, Medchal-Malkajgiri district, Telangana. It is registered with the Telangana RERA as P02200000371 (status: On-Going Project). The approving authority named in the filing is GHMC. The promoter filed a total site area of 51,536 sq m (12.7 acres) and 1 building on the approved plan. The proposed date of completion is 17/07/2023.
Description
LAKE FRONT D is a residential apartment project with 176 units in one tower of 10 floors on 51,536.02 sq m of land. TG-RERA lists it as an On-Going Project, with a proposed completion date of 17/07/2023.
- Project type
- Residential (apartment)RERA filing
- Units
- 176RERA filing
- Towers
- 1RERA filing
- Floors
- 10RERA filing
- Land area
- 51536.02 sq mRERA filing
- Possession
- 17/07/2023RERA filing
- Status
- On-Going ProjectRERA filing
Gallery


Configurations & sizes
For 2BHK homes, the carpet area measured from approved drawings is not available; the TG-RERA filing records 87 units, 73 bookings and 83.76 sq m saleable area. For 3BHK homes, the carpet area measured from approved drawings is not available; the filing records 89 units, 79 bookings and 119.52 sq m saleable area. Carpet-area figures should be verified against the drawings.
| Type | Carpet | Saleable | Source |
|---|---|---|---|
| 3BHK | 101.26 Sq.mt. - 119.52 Sq.mt. | 119.52 sq m | RERA filing |
| 2BHK | 74.78 Sq.mt. - 88.72 Sq.mt. | 83.76 sq m | RERA filing |
| 3 BHK Builder Floor | 1195 Sq. Ft. | magicbricks |
Amenities
The project’s disclosed amenities include shared recreational and community facilities alongside listed site infrastructure.
- Green Strip/TOT LOT/Park
- Community Buildings
- 35,000 sq.ft clubhouse
- lush landscaping
- Swimming Pool
- Security
- Reserved Parking
- Banquet Hall
- Gymnasium
- Indoor Games Room
- Internet/Wi-Fi Connectivity
- Kids play area
Specifications
- construction technology
- innovative German construction technology
- doors
- Main Door: Teakwood doorframe with both sides Teak Veneer Shutter
- doors
- Internal Doors: Non-Teakwood Frames with Flush-type Door Shutters
- doors
- Doors: Synthetic Enamel Paint for Door Shutters
- electrical
- Modular Switches: Siemens Delta Vega or Equivalent
- electrical
- Copper Wiring with ISI mark
- elevators
- 6 Passenger Elevators
- flooring
- Hall, Dining Room: Vitrified Tiles (24”x24”) of Asian or Equivalent
- flooring
- Bedrooms, Kitchen: Porcelain Tiles (16”x16”) of Asian or Equivalent
- flooring
- Balconies, Utility: Rustic Tiles (16”x16”) of Asian or Equivalent
- flooring
- Common Area: Industrial Vitrified Tiles (12”x12”) of Johnson or Equivalent with MS Railing
- flooring
- Flooring: Anti-skid Ceramic Tiles (12”x12”) of Bell or Equivalent
- flooring
- Interlocking Paver Tiles Flooring
- hardware
- Main Door: 6" Lock of Dorset or Equivalent
- hardware
- Internal Doors: Sheel Lock with Aluminium Hardware
- kitchen
- Granite Platform with Nirali or Equivalent Stainless Steel Sink,2' height dadoing with 8"x12" Glazed Tiles of Asian make
- plumbing
- Plumber - CP fittings or Equivalent Cera or Equivalent
- power backup
- Power back-up for Corridor Lighting and Elevators
- structure
- RCC Footings & Slabs without Beams
- structure
- Load Bearing RCC Walls
- tiles
- Glazed Tiles: 8"x12" White up to 7' height of Asian or Equivalent
- walls
- Internal Walls: Luppam with OBD Paint
- walls
- External Walls: Apex Exterior Painting
- windows
- Powder - coated Aluminium Frame with Glazed Open-able Shutters and Safety Grills
Location & connectivity
The project is in Kapra, Keesara mandal, Medchal-Malkajgiri district, PIN 500062. Nearby places listed by the developer’s marketing include Sainikpuri Main Road (1.5 KM), ECIL (3 KM), and Foster Billabong High International School (1.1 Km).
- SAINIKPURI MAIN ROAD1.5 KM
- ECIL3 KM
- TIRUMALAGIRI X ROAD6 KM
- SECUNDERABAD CLUB8 KM
- TARNAKA9 KM
- JUBILEE BUS STATION9 KM
- SECBAD RAILWAY STATION9 KM
- PARADISE10 KM
- Theresa School2.8 Km
- Foster Billabong High International School1.1 Km
- Shantiniketan International School4.5 Km
- Vampuguda Bus Stop1.3 Km
Promoter
The promoter is JANAPRIYA PROJECTS, a partnership, and the record lists seven other registered projects. Its official website is janapriya.com; T.A.J SANDEEPA is named as architect and R SAMBASIVA RAO as structural engineer.
Additional details
Filed vs marketed
The TG-RERA filing identifies the locality as KAPRA, while the developer’s marketing identifies it as SAINIKPURI.
- Locality: magicbricks says SAINIKPURI; the RERA filing says KAPRA. magicbricks
Sources & web results
- Janapriya Ventures: 41 Year Old Real Estate Company of ...janapriya.ventures
- Janapriya Lake Front in Sainikpuri, Hyderabadmagicbricks.com
- Janapriya Lake Front D in Kapra, Secunderabadhousing.com
- Janapriya Lake Front RERA Details - P02200000371, ...squareyards.com
- Janapriya Lake Front in Kapra, Hyderabadbuysft.com
- 3 BHK Apartment / Flat for sale in Janapriya Lake Front ...99acres.com
- Janapriya Lake Front in Kapra, Hyderabadestatedekho.ai
Public RERA registration record
Telangana RERA, as filed by the promoter.
- Registered name
- LAKE FRONT D
- Developer / Promoter
- JANAPRIYA PROJECTS
- Project type
- Residential
- RERA Registration No.
- P02200000371
- Registration Status
- On-Going Project
- Approved on
- 18/07/2017
- Proposed completion
- 17/07/2023
- Approving authority
- GHMC
- Total site area
- 51,536 sq m (12.7 acres)
- Approved built-up area
- 24,219 sq m (6.0 acres)
- Buildings (approved plan)
- 1
- Locality
- KAPRA
- Mandal
- Keesara
- District
- Medchal-Malkajgiri
- PIN code
- 500062
- Documents on File
- 33
Frequently asked questions
Is LAKE FRONT D registered with Telangana RERA?
Yes. LAKE FRONT D is registered with the Telangana Real Estate Regulatory Authority as P02200000371; the registration status is On-Going Project.
Who is the developer of LAKE FRONT D?
The promoter named in the RERA registration is JANAPRIYA PROJECTS.
Where is LAKE FRONT D located?
LAKE FRONT D is in KAPRA, Keesara, Medchal-Malkajgiri, Telangana (500062).
When will LAKE FRONT D be completed?
The promoter's proposed date of completion filed with RERA is 17/07/2023. This is the promoter's declaration, not a guarantee.